Today saw some work which was very apparent. The carpenters have been busy putting up the weatherboard cladding and the rendering to the front has started. The facade is now really taking shape!
According to MyMetricon, the Lock-up stage is scheduled to be complete on 25 March which is only next week. There seems to be still a bit of work to go before Lock-up is complete including putting up the garage roof truss and roofing. And they can’t do this until they finish with the balcony, first floor cladding and render to the first floor so they remove the scaffolding which is blocking the garage roofing work.