Day 93: Bricks delivered and house is wrapped

8 02 2013

day93-4We didn’t get on site today, but on our drive by after work we saw that the first floor is now also wrapped in blue.  The whole house looks like a smurf hut!

The scaffolding is gone which means most of the first floor external frame and wrapping is complete.  However, we are not sure if the wrapping is totally finished as there are a few loose bits hanging loose and just flapping about and there are parts still not fully covered.

We noticed that the bricks got delivered today.  Bricking should start next week.  Our bricks are Boral Mocha and from what we can see it has some nice blue tinge to it.

day93-3

Front view of house – lots of bricks in the foreground

day93-2

Side of house

day93-1

Bricks delviered – our bricks are Boral Mocha

Brick - Boral Mocha

Brick – Boral Mocha

C&K

Advertisements

Actions

Information

2 responses

10 02 2013
Andrew

Woohoo guys, it is starting to come together and looking like a home. What is current scheduled date to get keys??

16 02 2013
ournolanhome

Hi Andrew, at this stage if all goes well we could be in around June.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s




%d bloggers like this: