103 blog posts and 40,000 page views later…

27 05 2013

Overnight we have reached 40,000 page views!!! Woo hoo!

The blog visits has reflected our journey to date, a bit slow at the start but the last 6 months has seen good progress.

Thanks for dropping by for a visit.  And for those who are building or about to do a build with Metricon, hopefully our journey and advice has been helpful.

blogstats_may2013

C&K

Advertisements




Day 199: UFOs and Window Dressings

25 05 2013

Most of this week has been internal work.  The plumbers have been busy fitting the showerheads, taps, toilets, bathtubs and basins.  The bathrooms are now slowly looking more and more complete.

day199-1

Master Ensuite

day199-2

Shower head in the Master Ensuite

day199-8

Kitchen sink and tap

day199-4

Bathtub in upstairs bathroom

day199-7

Nice looking tiled shower base

The electricians have also been busy fitting off the light switches, ceiling light battens, powerpoints, exhaust fans and smoke detectors.  We added a lot of additional light points throughout the house for future downlights, and as a result the ceiling is littered with numerous Unsightly Fixed Objects (UFOs), also known as Conical Shades that comes standard with each light batten fitting.

Conical Shade and light batten

Conical Shade and light batten

These will look much better when we replace them with downlights.

Light battens

Ceiling full of Conical Shades

Quadruple powerpoint and tv point

Quadruple powerpoint and tv point

It’s been great to see the fit offs progressing well.

We have been spending a bit of our time looking at curtains the past few weeks and today we went to Dollar Curtains in Doncaster to finalise our selections.  They will take 6-8 weeks to produce which is why we wanted to order them now – they should be ready around the same time we get the handover from Metricon.  We have been pleased with curtains and prices from Dollar Curtains in the past.  The folks at Dollar Curtains, in particular Robyn were great – they were very friendly, helpful and thorough.

dollarcurtains_doncaster

Dollar Curtains, 1002 Doncaster Rd, East Doncaster, VIC

C&K





Day 196: Fit offs commenced

22 05 2013

plumberMonday saw the start of the plumbing fit offs including toilets, taps, bathtubs and basins.

The electricians have also been around to do some of the electrical fit offs.  Due to structural elements of the house we have had to shift a couple of the powerpoints to another location.

Tiling is almost complete – the laundry splashback is the only remaining tiling yet to be completed.

The majority of the painting is done – the painters will be back towards the end to do the touchups.

C&K





Day 192: Tiling progress

18 05 2013

Day164-1Tiling was the main activity this week.  The tilers started on Tuesday and 4 days later it is almost complete.  We only went with the tiling to the wet areas – powder room, bathrooms and laundry.  We also went with the standard (minimal) tiling.  We did consider full height and and half height tiling, but didn’t think it was worth the added expense (tiles and labour).

Our main colours for the bathroom are Harmony Beige for the floor and wall and Minimal Chocolate for the shower walls.  Here’s our post on the tile selections.

Day192-1

Powder room

In the powder room shower we have added a tile strip to break up the colour a bit and to provide a bit of a feature.

Day192-5

Powder room shower

And here’s a photo of the layout of the tiled shower base.

Day192-8

Day192-6

Laundry

The two bathrooms upstairs have a shower recess.

Day192-2

Master bedroom ensuite

Day192-3

Master bedroom ensuite

The tiles used in the balcony is Select Taupe.

Day192-4

C&K





Day 189: Photos of garage doors

15 05 2013

day189-2Here’s some photos of the garage doors.  The colour of the garage door goes well with the other colours we have selected and matches well with the timber stains on the door and window frames.  The gables above the garage still need to be stained with Cabot’s in Rich Walnut colour which should make it match the door better.

Overall we are very happy with how the whole facade is coming together!

Kristen met the tilers from Beaumont Tiles yesterday and they went through how the tiles will be laid out.  As our two main tiles are slightly different sizes they explained how in some areas the tiles will not line up.  It was really good that they explained this as it helps manages our expectations of how the final layout will look.  The tiling should be completed by this week.

The latest update from Simon indicated that the electrical and plumbing fit outs will start next week and the painting will finish on Saturday.  And Simon mentioned he will continue to follow up on a few quality issues.  Looks like we are making good progress – great job Simon & Metricon.

Front of garage: Gliderol Panel Glide - Classic Cedar

Front of garage: Gliderol Panel Glide – Classic Cedar

day189-4

Rear of garage: Roller-a-Door - Evening Haze

Rear of garage: Roller-a-Door – Evening Haze

C&K





Day 187: We have garage doors

13 05 2013

Today saw the garage doors being installed to the rear and front of the garage.  As it is getting dark early as we head towards winter, photos will have to wait for another day.

We have started to get in touch with some landscapers to provide quotes for design and construction of our front and rear yards, in particular the hard landscaping needs.  We want to have the landscape done soon after handover.

Tiles start tomorrow!!!

C&K





Day 186: Drip Drip Drip …

12 05 2013

It’s been a little over two weeks since our last post.  The exciting news is that painting has started although sadly it stopped almost as soon as it began.   Unfortunately the plasterers had hit a water pipe with a screw and a leak had slowly developed which had gradually got worse. This was  discovered over the Anzac day long weekend when some water was found on the floor in bedroom 4.  The water leaking increased and found itself into the first floor ceiling and onto the ground in the family-kitchen area.

Day171

Water pooling in Bedroom 4 – coming from behind the plaster and skirting

The green L & H on the concrete slab below are areas where it needs to be leveled before floorboards can be installed.  L – indicating it is low and H – indicating it is high.  These were later leveled out with cement.

Day172-1

Water from the ceiling dripping onto the ground floor

Day172-2

Water damage in ceiling.

Once alerted to the issue our Site Manager, Simon promptly organised the plumber to investigate and fix the leak.  Once the leak was fixed, parts of the damaged plaster and skirting were replaced.

Ceiling replaced and re-plastered

Ceiling replaced and re-plastered

We have been really pleased that Simon acted on this issue straight away and made sure it was fixed quickly.  Whilst the water damage issue is not ideal, the positive from the situation is that it occurred at this stage before any floor coverings had been laid.  In the end we have probably been delayed by about 2 weeks. The good news is we are now back on track and painting has recommenced.

Other progress made in the past 2 weeks include:

  • Completion of the external cladding to the rear of the house
  • Completion of the gables above the garage
  • Cleaning of the ground floor bricks
  • Plumbing works including installation of downpipes
  • And various quality issue fixes around the house
Day185-9

Last of the cladding now installed – just needs to be painted.

Day185-11

Gables installed above garage. You can also see downpipes connected to the house.

The base coats of painting to the house have been done and some of the staining of the timber windows have started.  Here are some photos of the painting progress:

Day185-3

Rumpus

Day185-4

Study doors with Cabot Stain – Colour Rich Walnut

Day185-7

Family-Kitchen area. The ceiling where it was water damaged is now fixed up, good as new.

Day185-8

Kitchen area

Day185-5

Master Ensuite

Day185-6

Stairs and upstairs leisure room

Day185

Front door with Cabot Stain – Colour Rich Walnut. Door handled installed.

Day185-2

Siting room window stained

We got a call from Beaumont tiles today, to say that tiling will start on Tuesday. They have invited Kristen to come and have a look at the tiles before they start and discuss the layout which we weren’t expecting but are quite pleased about.

We also had Dollar Curtains and Blinds come in to do a measure and quote for all of our window coverings. We are keen to have these ready to go once handover takes place. Simon was happy to meet us on site so we could do this which was great. it will take 4-6 weeks for the curtains to be made once we confirm what we want and 6-8  weeks for plantation shutters which we are planning to get in a few of the rooms.

C&K