Day 218: Carpets are in, Flooring Complete

13 06 2013

Yesterday saw the remaining of the Timber Floor completed – took 2 days in total to complete.  And yesterday the carpet also went in.  Looks like the flooring is complete, except for a few edgings between the timber floor, tiles and carpet.  We are glad the grey concrete which we have been staring at for the last 218 days is now gone.  The whole house has that new carpet smell.

 

day217-3

Siting Room

Siting Room

Upstairs landing area

Upstairs landing area

Master Bedroom

Master Bedroom

C&K





Day 215: Timber floors goes in

10 06 2013

day215-6Today saw the start of the timber floorboards installation.  We upgraded the laminated floors included in our promotion to Timber Floors – Boral Blackbutt.

The locations of the timber floor includes Entry (through to Kitchen), Kitchen, Walk-in Pantry, Family room, Dining room and storage under the stairs.  The timber floors are installed over a high density foam, moisture resistant underlay.

Note – if flooring is included in your purchase as part of a promotion, you should check to see if this includes the storage area under the stairs.  Normally this area is NOT included and you will need to add it in.  Otherwise when you open the door to under the stairs you will just have concrete which we didn’t think it would look too nice.

day215-7

The timber floors really start to transform the look and feel of the rooms – it really brightens up the space compared to the dull concrete.

There are a still a few fit off and painting activities to go and we were worried about the floor being damaged.  However, looking through the contract we found that there is a “Protective sheeting will be laid over the completed timber floor to provide protection against accidental damage during the final stages of construction. The protective sheeting becomes the responsibility of the client after handover.” This protective sheeting will also be handy when we move our possessions into the house.

day215-5

Timber floors in the dining area

Timber floors in the WIP

Timber floors in the WIP

Timber floors in the kitchen

Timber floors in the kitchen

View of the timber floors in the kitchen area

View of the timber floors around the kitchen area

The last week has also seen part of the glass splashback installed in the kitchen.  The colour of the splashback took a bit of time for us to warm to – at first we thought it may have been too dark, but over time we think it does go well with the Cesarstone bench.

Glass splashback and ceasar stone bench top

Glass splashback and ceasar stone bench top

The tiler has been back to tile around the glass backing boards in the powder room, bathroom and ensuite.

Tiling around mirror - Powder Room

Tiling around mirror – Powder Room

Tiling around mirror - Bathroom

Tiling around mirror – Bathroom

Tiling around mirror - Ensuite

Tiling around mirror – Ensuite

The shower in the ensuite had an extra row of tiles added as the glass frame is higher.

Ensuite Shower

Ensuite Shower

We are looking forward to seeing the remainder of the timber floors installed this week.

C&K





Day 212 – Latest review of progress – Electrical Fitoffs

7 06 2013

powerpointIts been awhile since we have provided an update on the house.  This week Kristen met our Site Manager, Simon, on site for some plantation shutter measurements and to get an update on progress.  Things have been progressing well and looks like we can finally say we will have handover NEXT MONTH !!!  (assuming things keep going well).

Last time we saw a lot of the plumbing happening.  This time around we have seen a lot of the electrical fitoffs being done.  Many of the powerpoints, tv aerials and data points have been installed.  All the light fittings have been done including the light bulbs.

Many of the door handles have started to appear and the robes now have mirrored doors installed and fitted out with rails.  Also the windows have been cleaned and the fly screens have been installed.

day211-1

We have lights!

We are looking forward to replacing the light fittings with LED downlights and last weekend we have started to visit some lighting stores – we will need to purchase around 84.  That’s a lot of downlights!

day211-2

Kitchen

day211-10

Sitting Room – Kristen loves the feature wall!

During the electrical appointment we weren’t sure if we should got with 2 or 3 stair lights.  In the end we went with 2 and we are more than happy with our decision.

day211-9

Stair lights

day211-4

Light up the stairwells

day211-7

Mirrored doors for the robes – these were part of a promotion

day211-8

In the master bedroom we elected to have a set of double rails – one on each end of the WIR

day211-5

All our thrones (toilets) look like this

day211-3

Family room electrical fitoff – ready for some serious entertaining. 2 Tv aerials, 3 data points (CAT 6), quad powerpoint and a conduit for the TV cables

day211-6

Door handle

A few things that still need following up:

  • A powerpoint in the kitchen needs to be relocated due to it being in the way of the glass splashback.
  • Water not draining properly along one side of the house
  • Brick mortar need fixing near kitchen (brick cleaners blasted some of the mortar out)
  • Laundry splashback still needs to be completed – looks like not enough tiles were ordered.
  • Pillars need to be re-rendered
  • Gables need fixing as it was not installed properly
  • Some replaster and plaster fixes

It’s really great to see things progressing well.  Floors should start sometime next week.

C&K





Landscape Design

2 06 2013

landscape-drawingWe are getting close to the completion of the house and the curtains have been ordered.  The next major item to organise is the landscaping.  With the wet weather, muddy conditions and young family we would like the landscaping started straight after we get possession of the keys.

daviscapes_logo

We have met Ben from Daviscapes and decided to engage him to put together a design as we felt he was a good fit for our needs.  Here is some info about Daviscapes – PDF.

We are looking at getting the whole landscape design done:

  • Landscaping including excavation, irrigation, drainage and garden beds
  • Retaining walls
  • Front yard fencing
  • Front portico
  • Rear alfresco/outdoor area
  • Lighting
  • Side concreting
  • Driveway concreting including crossover relocation

We are looking forward to seeing the first output of the design hopefully late next week.   Once we have the design we can use it to get quotes for the construction, that way we can get an apples-for-apples comparison.  Daviscapes can also perform the construction, but it all depends on how competitive they are.

We already have a list of a few landscape construction contractors that have been recommended by friends.  However, if anyone has any other recommendations please let us know.  We would love to hear from you.

C&K