READY….SET…..

19 09 2012

We got a phone call today from our Metricon CSC, Megan, to give us some great news, wait for it………we have a site RE(START) DATE – Thursday 27.09.2012!! That’s right, we will have a start by the end of next week!!

Great job from the folks at Metricon to get a response and a date on a site start quickly. Let’s hope it goes according to plan and no major issues from here onwards and we get some solid progress before Christmas.

Now when everyone asks “how’s things going with the house?” we can now provide a progress update rather than just saying “we’re still waiting for Metricon and the council to sort out the pipe”.

Easement back on the title

Today we also received a copy of the title with the easement back on the title as per the original creation.  A dashed line (cirecled in red) went missing in action at some stage between 1959 and 2011.  So when we did all our house designs and initial permit approvals, an easement was not considered.

Here’s something that made us laugh – when we read the title, we saw the following regarding the easement:

“…[we] give and grant unto the said [council] the full and free right and liberty to and for them their servants, agents, contractors and workmen at all times hereafter to enter and reenter upon and to pass and repass for all or any of the purpose hereinafter mentioned and either with or without horses or other animals carts or other carriages through over and along the land….”

Besides being a long sentence, there’s no mention of motorised vehicles or equipment.  So does that mean we can refuse entry if they don’t come with horses or carriages?  🙂

It will be 133 days (4.5 months) delay when site re(starts) next week.  In the end, the cause of all of this is a dotted line missing from the title!!!!!!!