The scaffolding has come down and we can finally see our beautiful house from the street in full frontal. Doesn’t it look pretty. 🙂
The gables are now how they should be. When they were first installed there was no recess.
C&K
The scaffolding has come down and we can finally see our beautiful house from the street in full frontal. Doesn’t it look pretty. 🙂
The gables are now how they should be. When they were first installed there was no recess.
C&K
It’s been a little over two weeks since our last post. The exciting news is that painting has started although sadly it stopped almost as soon as it began. Unfortunately the plasterers had hit a water pipe with a screw and a leak had slowly developed which had gradually got worse. This was discovered over the Anzac day long weekend when some water was found on the floor in bedroom 4. The water leaking increased and found itself into the first floor ceiling and onto the ground in the family-kitchen area.
The green L & H on the concrete slab below are areas where it needs to be leveled before floorboards can be installed. L – indicating it is low and H – indicating it is high. These were later leveled out with cement.
Once alerted to the issue our Site Manager, Simon promptly organised the plumber to investigate and fix the leak. Once the leak was fixed, parts of the damaged plaster and skirting were replaced.
We have been really pleased that Simon acted on this issue straight away and made sure it was fixed quickly. Whilst the water damage issue is not ideal, the positive from the situation is that it occurred at this stage before any floor coverings had been laid. In the end we have probably been delayed by about 2 weeks. The good news is we are now back on track and painting has recommenced.
Other progress made in the past 2 weeks include:
The base coats of painting to the house have been done and some of the staining of the timber windows have started. Here are some photos of the painting progress:
We got a call from Beaumont tiles today, to say that tiling will start on Tuesday. They have invited Kristen to come and have a look at the tiles before they start and discuss the layout which we weren’t expecting but are quite pleased about.
We also had Dollar Curtains and Blinds come in to do a measure and quote for all of our window coverings. We are keen to have these ready to go once handover takes place. Simon was happy to meet us on site so we could do this which was great. it will take 4-6 weeks for the curtains to be made once we confirm what we want and 6-8 weeks for plantation shutters which we are planning to get in a few of the rooms.
C&K
Today we met Simon on site first thing in the morning to go through the latest updates and a walkthrough of the defect fixes from our independent building inspector’s report. When we arrived it was a busy morning on site with lots of activity:
We spent about an hour with Simon walking through the house and going through the items in the report. There were a few things we couldn’t see anymore as it was covered up, but we have asked Simon to send us the photos that were taken of the fixes. There were a couple of items that weren’t fixed and Simon took it upon himself to rolls his sleeves up and fix them. We are really pleased that Simon and Metricon are taking the effort and additional time to fix the defects to make sure the house is right.
In the afternoon, the carpenters were back to install the gables to the front of the roof and start on the weatherboard cladding to the rear of the house.
Ready for some photos? Here’s what we took today. Enjoy – we sure did 🙂
So what’s next? Well lock-up completion is not far away, most likely just after Easter break (early April). Which means another payment milestone. The scaffolding will come down this coming Friday. Next week will see the garage truss and roof installed, final coats of the render (coloured) and a site clean.
C&K